Replacement of inner casing (gas boiler pass) of utilizer boiler
Location of object: Kohtla-Järve
Customer: AS VKG Oil
Brief description of work: Disassembly of an old КУ-126 boiler. Designing project documentation for installation of a boiler into horizontal position, with further change over to the designed position. Replacement of inner casing (gas boiler pass) of an utilizer boiler КУ-126 in the inter-casing space of Petroter I installation. Follow on development and assembly of pipes for binding of utilizer-boiler. Installation of service platforms. Restoring insulation of boiler and pipelines.
Finnish date: 2017


Installing a boiler no.4 Е-135-3, 2-420ДГ
Location of object: Kohtla-Järve
Customer: UAB Energetikos paslaugų ir rangos organizacija
Brief description of work: Installing components of a boiler no.4 Е-135-3, 2-420ДГ and service platforms. Installing pipeline of a feed unit of a steam-line, the steam-line, a gas pipe. Installing gas boiler passes and recirculation air ducts to burner of boiler no.4. Installing a gas boiler pass for smoke gases. Installing continuous blowdown expanders. Restoring insulation of boiler and pipelines.
Finnish date: 2017
Design and repair work on tank no.7 (montejus) of sulphuric acid storage at the Põhja SEJ projekteerimine
Location of object: Kohtla-Järve
Customer: OÜ VKG Energia
Brief description of work: Disassembling an old montejus, disconnecting a tank from technological layout, from sulphuric acid pipeline and compressed air. Manufacture and assembly of montejus and supports, assembly on-site. Connection to the existing technological layout.
Finnish date: 2017
50% increase of a share of tar gas burning in boiler no.1, block 8
Location of object: Eesti Elektrijaam
Customer: AMEC FOSTER WHEELER
Brief description of work: Modernization of boiler no.1 for block no.8 with the aim of increasing a share of tar gas burning. Installing new burners and modernization of the existing ones. Installing worms for ash removal. Installing gas boiler passes.
Tööde tähtajad: 2017
Construction of an Oil Products Terminal, a Pump Station and a Railway and Truck Load Trestle
Location of object: Mockavos terminalas, Lithuania
Customer: UAB Mockavos terminalas
Brief description of work: Building a tank battery of pump house, railway load rack and truck terminal.
Finnish date: 2017